| No. | Company | Consultant | Work Details | Value Of Work | Execution Period |
|---|---|---|---|---|---|
| 1 | SRM Hospital | M/s. K.R.Associate Chennai | STP, ETP Gen. Set, Structural Steel Ramp Bulding & Interior | 235 Lacs | 12 Months |
| 2 | Forits Malar Hospital Chennai | M/s. Technicalia Consultant PVT LTD | Civil & Interior | 50 Lacs | 3 Months |
| 3 | A.S Cargo Movers(P) LTD | M/s. C.R Narayana Rao Architects & Engineers | Loading Platform | 100 Lacs | 2 Months |
| 4 | Independent Bungalow | Own Turnkey Projects | Resident | 75 Lacs | 6 Months |
| 5 | M/s. Malar Hospital Chennai | M/s. Technicalia Consultant PVT LTD | Civil & Interior | 250 Lacs | 9 Months |
| 6 | Premier Metal Finishers | Own Turnkey | Factory Bulding | 75 Lacs | 9 Months |
| 7 | M/s. Forits Malar Hospital Chennai | M/s. Technicalia Consultant PVT LTD | Civil & Interior | 250 Lacs | 9 Months |
| 8 | Sabols Industries | Own Turnkey | Expansion | 50 Lacs | 6 Months |
| 9 | M/s. IIBT at Padapai | M/s. IIBT | Compound Wall | 65 Lacs | 6 Months |
| 10 | International Institute of Bio Technology & Toxicology | M/s. C.R. Narayana Rao Architects & Engineers | Lab Building Expansion | 60 Lacs | 5 Months |
| 11 | M/s. Forits Malar Hospital Chennai | M/s. C.R. Narayana Rao Architects & Engineers | Floor Renovation | 40 Lacs | 4 Months |
| 12 | B & C Projects Ltd | M/s. C.R. Narayana Rao Architects & Engineers | Power Projects | 320 Lacs | 12 Months |
| 13 | Sabols Industries Packaged Drinking Plant, Thodugadu Village, Tiruvellore Dist | M/s. K.R.Associate Chennai | Own Turnkey Projects | 50 Lacs | 6 Months |
| 14 | Saint Gobain Glass India LTD | M/s. Escad | Boiler House | 95 Lacs | 6 Months |
| 15 | Dunlop India Limited, Chennai | M/s. C.R Narayana Rao Architects & Engineers | Boiler House and Boiler & Nessary Foundation Work | 250 Lacs | 6 Months |
| 16 | Sabols Industries Packaged Drinking Plant, Thodugadu Village, Tiruvellore Dist | Own Turnkey Projects | Expansion | 100 Lacs | 4 Months |
| 17 | IIBT, Padapai, Kancheepuram | M/s. C.R Narayana Rao Architects & Engineers | Lab – R.C.C Building | 75 Lacs | 120 Days |
| 18 | HWASHIN Automatiive India Pvt. Ltd. Sripermbudur | M/s. C.R Narayana Rao Architects & Engineers | Building R.C.C Road Work | 125 Lacs | 150 Days |
| 19 | Sabols Industries Packaged Drinking Plant, Thodugadu Village, Tiruvellore Dist | Own Turnkey Projects | Land Development, Factory Building Other Connected Civil Work | 320 Lacs | 9 Months |
| 20 | Saint Gobain Glass (I) LTD, Sripermbudur | HUMPHREY GLASWGOW CONSULTANT LTD., MUMBAI | Factory Execution & Maintenance | 200 Lacs | 6 Months |
| 21 | Wheels India Ltd, Padi, Chennai | Own Turnkey Projects | R.C.C Road Work | 150 Lacs | 3 Months |
| 22 | AXLES INDIA LIMITED, Sripermbudur | Own Turnkey Projects | Factory Building | 140 Lacs | 4 Months |
| 23 | BTR Mother Sons Automative Ltd | M/s. Dalal Consultant | Expansion | 320 Lacs | 9 Months |
| 24 | Banfligioli Ltd., Thirumudivakkam | Own Turnkey Projects | Factory Expansion | 200 Lacs | 12 Months |
| 25 | Donmghee Vision Ltd., Irungattukottai | M/s. Fishner, Chennai | Office Building Research Center | 150 Lacs | 6 Months |
| 26 | HIS Automatice Ltd., Sripermbudur | M/s. C.R Narayana Rao Architects & Engineers | Factory Building | 140 Lacs | 4 Months |
| 27 | SRF Ltd, Manali | M/s. Dalal Consultant | Factory Expansion | 90 Lacs | 12 Months |
| 28 | Lumax Samplips Ltd., Irungattukottai | M/s. Fishner, Chennai | Office Building And Power House | 150 Lacs | 6 Months |
| 29 | Commercial Complex, Kottivakkam | M/s. C.R Narayana Rao Architects & Engineers | Factory Building | 120 Lacs | 9 Months |